ELECTRICITY: Ogba, Magodo, Others, To Experience Eight-week Blackout From October 11

October 5, 2021
by
TCN Threatens Defaulting Discos, Gencos After Aba Power Clampdown

Ikeja Electric Plc has announced that communities under its franchise network in Lagos State will experience an eight-week power outage.

Chief Technical Officer of the company, Jide Kumapayi, who disclosed the development, noted that it is to enable the Transmission Company of Nigeria (TCN) to re-conduct its 132KV lines.

Join our WhatsApp Channel

According to him, the upgrade is coming at a time when the capacity of most of the 132KV lines have become limited largely due to time and usage, leading to under-utilization.

In his words, “the TCN is currently embarking on the upgrade of 132 KV lines from Ikeja West to Ota and this activity is phased into four stages. This is the second stage and TCN is upgrading the 132kv lines with more robust and sophisticated replacements which provide an opportunity to increase power evacuation for improved supply to customers as well as offering excellent conductor capacity which can withstand very high voltage,” he was quoted as saying in a post on Ikeja Electric’s website.”

“The upgrade which is set to commence on Monday, October 11, 2021, will affect customers within Oregun, Anifowoshe, Ojodu, Magodo, Omole, Oba-Akran, Oke-Ira, Ogba, Omole Phase 1 and parts of Ikeja, between the hours of 8:00am and 6:00pm daily, for eight weeks.”

Kumapayi, however, assured that the company’s technicians will be on standby to give support when needed during the upgrade.

“We believe it will be for the benefit of our customers at the end of the day and will also allow Ikeja Electric to invest more in our Network to improve power supply to customers under our network. So we want to appeal to our customers to bear with us as this exercise will be beneficial toward the improvement of power supply in our network.” He added.

+ posts
Previous Story

Nigerian Military Launches Three Operations To Battle Insecurity

Naira Devaluation Will Cause Negative Impact Of $22m On Revenues, Airtel Africa Says
Next Story

Airtel Nigeria To Buy Back Minority Shareholding At N55.81 Per Share

Featured Stories

Latest from Power

Ethiopia Completes $5 Billion Africa’s Largest Dam In 14 Years

Ethiopia has inaugurated the Grand Ethiopian Renaissance Dam (GERD), Africa’s largest hydroelectric project, in a move hailed in Addis Ababa as a generational victory but viewed downstream as a looming threat to water security. Standing 170 meters tall and nearly two kilometers
Previous Story

Nigerian Military Launches Three Operations To Battle Insecurity

Naira Devaluation Will Cause Negative Impact Of $22m On Revenues, Airtel Africa Says
Next Story

Airtel Nigeria To Buy Back Minority Shareholding At N55.81 Per Share

Don't Miss

How Loss Of Over $5 Trillion In U.S. Stock Exchange Affects Nigeria

Investors In Stock Market Lost N27.80bn, As Equity Cap Record Steep Drop

Over N27.80 billion was lost in the Nigerian stock market

APC Hails Supreme Court Judgement In Favour Of Tinubu

The All Progressives Congress (APC) has applauded the Supreme Court