TCN Threatens Defaulting Discos, Gencos After Aba Power Clampdown

ELECTRICITY: Ogba, Magodo, Others, To Experience Eight-week Blackout From October 11

October 5, 2021
1 min read

Ikeja Electric Plc has announced that communities under its franchise network in Lagos State will experience an eight-week power outage.

Chief Technical Officer of the company, Jide Kumapayi, who disclosed the development, noted that it is to enable the Transmission Company of Nigeria (TCN) to re-conduct its 132KV lines.

Join our WhatsApp Channel

According to him, the upgrade is coming at a time when the capacity of most of the 132KV lines have become limited largely due to time and usage, leading to under-utilization.

In his words, “the TCN is currently embarking on the upgrade of 132 KV lines from Ikeja West to Ota and this activity is phased into four stages. This is the second stage and TCN is upgrading the 132kv lines with more robust and sophisticated replacements which provide an opportunity to increase power evacuation for improved supply to customers as well as offering excellent conductor capacity which can withstand very high voltage,” he was quoted as saying in a post on Ikeja Electric’s website.”

“The upgrade which is set to commence on Monday, October 11, 2021, will affect customers within Oregun, Anifowoshe, Ojodu, Magodo, Omole, Oba-Akran, Oke-Ira, Ogba, Omole Phase 1 and parts of Ikeja, between the hours of 8:00am and 6:00pm daily, for eight weeks.”

Kumapayi, however, assured that the company’s technicians will be on standby to give support when needed during the upgrade.

“We believe it will be for the benefit of our customers at the end of the day and will also allow Ikeja Electric to invest more in our Network to improve power supply to customers under our network. So we want to appeal to our customers to bear with us as this exercise will be beneficial toward the improvement of power supply in our network.” He added.

+ posts

Latest from Power

TCN Adds 120MW To Nigeria’s Power Grid 

TCN Adds 120MW To Nigeria’s Power Grid 

The Transmission Company of Nigeria (TCN), says 120 Megawatts (MW) has been added to the national grid, in a move aimed at boosting electricity supply across the country. This came as TCN
Nigerian Electricity Regulatory Commission (NERC) has announce reduction of electricity tariff for band A customers from N225 per kilo watt hour (kWh) to N206.8kWh with effect from May 2024.

NERC Sets Grid Integration Deadline For GenCos

The Nigerian Electricity Regulatory Commission (NERC) has issued an order mandating all grid-connected power generation companies to fully integrate their operations with the new Supervisory Control and Data Acquisition (SCADA) and Energy