Gas Supply To Geometric Power Resumes As More People Now Receive Electricity In Aba

April 23, 2025
by

Gas supply to the 188MW Geometric Power Plant in Aba, Abia State, has resumed three days after it was suspended.

The suspension was due to what industry experts called a process upset and a gas leak in the associated gas gathering (AGG) facilities of a leading indigenous oil and gas company in the neighbouring Rivers State.

Join our WhatsApp Channel

Gas supplies resumed Monday night, and by 9:02 pm, one of the 47MW turbines had started to generate 25MW, according to Dike Ejike, a mechanical engineer and power consultant, who confirmed the development.

“By 11 am today, it was generating 37.44MW, and by 2 pm, it had risen to 39.5MW”, said Ejike. “It is increasing gradually”.

The power consultant disclosed that the quantum of power made available to Aba people in nine of the 17 local government areas in Abia State is now almost 65MW because Aba Power, the electricity distributing company of the Geometric Power group, still receives 25MW from the Niger Delta Power Holding Company (NDPHC) to augment available power from the Geometric Power Plant.

He explained: “More individuals, businesses, industries, non-profit organisations, and communities have been receiving supplies since the gas supply issue was resolved, and supplies have been growing.”

A Lagos-based power consultant who was a top executive with the defunct Power Holding Company of Nigeria (PHCN), Engr Cliff Eneh, applauded Heirs Energies, operator of the Oil Mining Lease (OML) 17, which produces gas supplied to Geometric Power and some other customers, for working around the clock to resolve this issue.

READ ALSO: Aba Power Seeks Increased Gas Supply To Boost Electricity Services

“The engineers and the entire technical team at Heirs Energies”, he observed, “worked tirelessly and efficiently in a way typically associated with international oil companies (IOCs) like Shell, ExxonMobil, TotalEnergies, Chevron, Agip, British Petroleum, etc. But Heirs Energies is a new indigenous Nigerian firm giving the nation hope.”

“They did not care that it was a weekend or the Easter holiday period, but worked with tremendous commitment and dedication to fix the problem, so that electricity customers in the Aba Ring-fenced Area would have light during this critical period.”

Engr Eneh expressed optimism that the Heirs Energies team would display the same zeal and competence in fixing gas supply issues whenever they occur.

“I am confident that Nigerian engineers will go places if given the opportunity,” he concluded.

+ posts

Featured Stories

Latest from News

Court Orders EFCC To Produce Emefiele On November 8 Amidst Discrepancy

Emefiele Trial: Witness Blames Cash Scarcity on Commercial Banks

A witness for Nigeria’s anti-graft agency told a federal court on Tuesday that some commercial banks hoarded newly redesigned naira notes during the cash crunch that followed the Central Bank of Nigeria’s currency overhaul in late 2022 and early 2023. Chinedu Eneanya,
Previous Story

Black Market Dollar (USD) To Naira (NGN) Exchange Rate Today, 23rd April 2025

Next Story

Wema Bank records N433bn revenue, net income increases by 139.7%

Don't Miss

150 Indian Firms Invest $27bn In  Nigeria - High Commissioner

150 Indian Firms Invest $27bn In  Nigeria – High Commissioner

In a bid to strengthen bilateral ties between Nigeria and
Leaked S3x Tape: Court Slams Oxlade With N5m Fine

Leaked S3x Tape: Court Slams Oxlade With N5m Fine

A Lagos High Court has awarded ₦5 million damages against