Gas Supply To Geometric Power Resumes As More People Now Receive Electricity In Aba

April 23, 2025
by

Gas supply to the 188MW Geometric Power Plant in Aba, Abia State, has resumed three days after it was suspended.

The suspension was due to what industry experts called a process upset and a gas leak in the associated gas gathering (AGG) facilities of a leading indigenous oil and gas company in the neighbouring Rivers State.

Join our WhatsApp Channel

Gas supplies resumed Monday night, and by 9:02 pm, one of the 47MW turbines had started to generate 25MW, according to Dike Ejike, a mechanical engineer and power consultant, who confirmed the development.

“By 11 am today, it was generating 37.44MW, and by 2 pm, it had risen to 39.5MW”, said Ejike. “It is increasing gradually”.

The power consultant disclosed that the quantum of power made available to Aba people in nine of the 17 local government areas in Abia State is now almost 65MW because Aba Power, the electricity distributing company of the Geometric Power group, still receives 25MW from the Niger Delta Power Holding Company (NDPHC) to augment available power from the Geometric Power Plant.

He explained: “More individuals, businesses, industries, non-profit organisations, and communities have been receiving supplies since the gas supply issue was resolved, and supplies have been growing.”

A Lagos-based power consultant who was a top executive with the defunct Power Holding Company of Nigeria (PHCN), Engr Cliff Eneh, applauded Heirs Energies, operator of the Oil Mining Lease (OML) 17, which produces gas supplied to Geometric Power and some other customers, for working around the clock to resolve this issue.

READ ALSO: Aba Power Seeks Increased Gas Supply To Boost Electricity Services

“The engineers and the entire technical team at Heirs Energies”, he observed, “worked tirelessly and efficiently in a way typically associated with international oil companies (IOCs) like Shell, ExxonMobil, TotalEnergies, Chevron, Agip, British Petroleum, etc. But Heirs Energies is a new indigenous Nigerian firm giving the nation hope.”

“They did not care that it was a weekend or the Easter holiday period, but worked with tremendous commitment and dedication to fix the problem, so that electricity customers in the Aba Ring-fenced Area would have light during this critical period.”

Engr Eneh expressed optimism that the Heirs Energies team would display the same zeal and competence in fixing gas supply issues whenever they occur.

“I am confident that Nigerian engineers will go places if given the opportunity,” he concluded.

+ posts

Featured Stories

Latest from News

Previous Story

Black Market Dollar (USD) To Naira (NGN) Exchange Rate Today, 23rd April 2025

Next Story

Wema Bank records N433bn revenue, net income increases by 139.7%

Don't Miss

Mixed Reactions Trail Nigeria’s Supreme Court Judgment On LG Autonomy

US Lawyer In Trouble For Using Chat GPT To File Case Reference

Steven Schwartz, a lawyer in New York, the United States
Broken Promises, Broken Trust: The Failure Of Government Communication In Nigeria

Broken Promises, Trust: Bane Of Government Communication In Nigeria

Communication Breakdown Between Nigerian Government and Citizens The relationship between