Geometric Power, National Control Centre Design Programme For Electricity Supply To Aba

Geometric Power Ltd and the National Control Centre (NCC) at Oshogbo in Osun State have developed a timetable on how electricity will be supplied to all parts of the Aba Ring-fenced Area in Abia State.

This comes after the commissioning of the Aba Independent Power Project (IPP) by Vice President Kashim Shettima on behalf of President Bola Tinubu last Monday.

Both parties reached the understanding yesterday following the visit of an NCC team on Thursday to the 188-megawatt Aba IPP and the inspection of its facilities the next day.

The IPP includes the 188MW thermal plant located in the Osisioma Industrial Layout of Aba and the Aba Power Electric Company set up to distribute power to the Aba Ring-fenced Area which comprises nine of the 17 local government areas in Abia State.

READ ALSO: Why Geometric Power Will Make A Difference In Electricity Supply In Aba – Expert

“Commercial electricity supply to the nine LGAs began yesterday”, an engineer with the Transmission Company of Nigeria (TCN) who is conversant with the timetable, told our correspondent on the condition of anonymity.

“It began with the release of 7MW, and 7MW will be added every week until the commissioning phase is over.”

Experts call the method the ramp-up process of commissioning.

With 7MW injected into the system weekly, according to Isaac Ayodele, a former engineer with the defunct Power Holding Company (PHCN ) who is now an energy consultant in Lagos, “all 47MW from the first General Electric (GE) turbine will be supplied to consumers by the end of this month.

“This will be double the quantum of electricity currently supplied to the Aba Ring-fenced Area by the Niger Delta Power Holding Company (NDPHC), which has been just 25MW for months.”

Ayodele continued: “By the end of April, power outages will be a thing of the past in all the 9 LGAs in Abia State serviced by Aba Power, Nigeria’s 12th electricity distribution company and the newest.”

The Geometric Power leadership has explained that the 47MW from the third GE turbine will be sent to the national grid, since Aba and its environs may not absorb more than 94MW right now.

There are indications, however, that the Southeast governors will press that the excess 47MW be sold to the Enugu Electricity Distribution Company (EEDC) for use in the five Southeastern states.

A source at the South East Governors Forum in Enugu who pleaded for anonymity told journalists: “We are finalising discussions on this matter”.

Admin

Recent Posts

SIM Boxing, And The Unboxing Of A Crime Syndicate

Boxes have a multitude of uses, and the word “box”, lends itself to diverse contexts.… Read More

45 mins ago

Customers To Get More Benefits As 9mobile Updates Its ‘MoreBusiness ComboPak’

One of the leading telecommunications companies in Nigeria, 9mobile, has updated its ‘MoreBusiness ComboPak’ offerings… Read More

1 hour ago

Court Restrains PDP From Removing Damagum As National Chairman

Federal High Court sitting in Abuja has given an Interim Order restraining the  Peoples Democratic… Read More

2 hours ago

TikTok Sues U.S. Government Over Sale Bill On ByteDance

TikTok has launched a lawsuit against the United States government over legislation threatening to force… Read More

3 hours ago

Cybersecurity Levy: Nigerian Govt Milking A Dying Economy – Obi

Presidential candidate of the Labour Party in the 2023 general election, Mr Peter Obi, has… Read More

3 hours ago

‘Why I Called My Song ‘Men Are Crazy’ – Simi

Nigerian superstar Simi has spoken up about the inspiration behind the controversial title of her… Read More

4 hours ago

This website uses cookies.